Project Update

Current status of the tower:

  • Structural Works : 100% completed.
  • Block Works : Ground to 12th Floor - 95% completed (approx), 13th Floor - 50% completed (approx)
  • Plaster Works : Ground to 11th Floor - 95% completed (approx).
  • Painting Works : Primer & Stucco - 1st to 11th Floor - 90% completed (approx).
  • False Ceiling Works : Bathroom & Kitchen Channel fixing - 1st to 6th Floor - 50% completed.
  • Tiling Works.
  • Kitchen Wall Tiles - 1st to 11th Floor - 90% completed.
  • Kitchen Floor Tiles - 1st to 8th Floor - 85% completed.
  • Bathroom Wall Tiles - 1st to 11th Floor - 85% completed.
  • Bathroom Floor Tiles - 1st to 11th Floor - 85% completed.
  • Flooring in Halls & Bedrooms - 1st to 11th Floor - 90% completed.
  • MEP Works.
  • Electrical Works - Ground to 11th Floor (1st & 2nd fix) - 90% completed (approx), 12th Floor - Work in Progress.
  • Drainage & Water Supply - Ground to 11th Floor (1st & 2nd fix) - 90% completed (approx), 12th Floor - Work in Progress.
  • Fire Alarm & Fighting Works - Ground to 11th Floor (1st & 2nd fix) - 80% completed (approx).
  • A/C Works - A/C Machines - 1st to 5th Floor - 90% completed (approx).
 