Project Update
Current status of the tower:

  • Structural Work completed 100%.
  • Block Works : Completed 100%.
  • Plaster Works : 1st to Roof Floor - Completed 100%.
  • Tiling Works : 1st to 13th Floor - All tiling works - Completed 95%, 14th Floor- Work in Progress.
  • Lift Works : Completed - Service Lift Started.
  • Wooden Doors : 1st to 12th Floor - Completed 90%, 13th Floor - Work in Progress.
  • Kitchen Cabinets : 2nd to 9th Floor - Completed 80% (approx.), 10th to 12th Floor - Completed 70% (approx.), 1st Floor - Work in Progress.
  • Primer & Stucco : 1st to 12th Floor – Completed 90%, 13th & 14th Floor – Completed 70%.
  • Vanity Counters : Upto 13th Floor - Completed 90% (approx).
  • MEP Works.
  • Electrical Works - 1st to 14th Floor - Completed 85% (approx).
  • Plumbing & Drainage - 1st to 14th Floor - Completed 90% (approx).
  • Fire Alarm & Fighting Works - 1st to 7th Floor - Completed, 8th to 14th Floor - Completed 75% (approx).
  • A/C Works - 1st to 14th Floor - Completed 90% (approx).
  • Gas Piping - 1st to 13th Floor - Completed 90% (approx).
 